Calculate concrete needed for steps by adding the volume beneath each tread and any landing, then including separately measured foundations and an ordering allowance. For solid steps, each section extends down to the prepared base. One cubic yard equals 27 cubic feet, according to NIST’s volume tables (2009), so you can convert your measured volume into the units used for delivery.
How do you measure steps without counting the landing twice?
Start with a side-view sketch showing the finished stair profile and the surface that supports the concrete. Add a top view if the width changes or the landing extends beyond the stairs. Measure inside the forms, where the concrete will actually go.
Record these dimensions:
- Width: the distance across the stairs.
- Tread run: the horizontal distance between successive riser faces. Model any projecting nosing separately if needed.
- Riser height: the vertical change between adjacent walking surfaces.
- Landing depth: the horizontal distance from the final riser to the back of the platform.
- Concrete height beneath each surface: the distance from the prepared base to that tread or landing.
Count vertical rises separately from horizontal treads. When the upper landing is the final walking surface, the last rise leads directly onto it. Adding another full tread at landing height would count concrete that may already belong to the platform.
Use the actual bottom boundary of the concrete. Finished ground beside the stairs may sit above or below that boundary, so measuring every height from adjacent lawn level can produce the wrong quantity.
Before finalizing dimensions, ask your local building department about permits, stair geometry, landings, handrails, guards, and foundation requirements. Have the support and connection details resolved before estimating materials. A volume calculation does not establish whether the stairs are structurally adequate or compliant.

What formula gives the volume of solid concrete steps?
For stairs that are solid concrete down to a level base, divide the side profile into vertical rectangular sections. Each section occupies the footprint of its own tread and extends from the base to that tread’s surface.
Section volume = width × tread run × height above the concrete base.
Add those sections, then calculate the landing as a separate block:
Solid landing volume = landing width × landing depth × height above the concrete base.
These blocks sit beside one another, so they do not overlap. Do not calculate a full rectangular block around the entire staircase unless you also subtract the empty space above the lower treads.
For equal tread runs and a constant width, you can shorten the arithmetic:
Tread-section volume = width × tread run × sum of the tread heights above the base.
This approach also handles unequal heights: enter each measured height individually. If the base slopes, the sections are no longer simple full-height rectangular blocks; calculate their actual cross-sectional shapes instead.
Keep all dimensions in the same unit before multiplying. When using inches throughout:
- Cubic feet = cubic inches ÷ 1,728.
- Cubic yards = cubic inches ÷ 46,656.
Both conversion factors come from NIST Handbook 44, Appendix C (2009). Keep unrounded results in your calculator until the ordering stage.
How much concrete would a staircase with an upper landing need?
Consider this hypothetical quantity example: a staircase with five equal rises, four exposed treads, and an upper landing. These are calculation inputs, not a construction specification.
Assume the stairs and landing are solid down to the same level concrete base, with these dimensions:
| Input | Example dimension |
|---|---|
| Stair and landing width | 48 inches |
| Height of each rise | 7 inches |
| Run of each exposed tread | 11 inches |
| Upper landing depth | 36 inches |
| Landing height above the base | 35 inches |
The exposed tread surfaces are at progressively greater heights. Calculate each section using its own full height above the base:
| Section | Calculation in inches | Volume in cubic inches |
|---|---|---|
| Lowest tread | 48 × 11 × 7 | 3,696 |
| Next tread | 48 × 11 × 14 | 7,392 |
| Next tread | 48 × 11 × 21 | 11,088 |
| Highest exposed tread | 48 × 11 × 28 | 14,784 |
| Upper landing | 48 × 36 × 35 | 60,480 |
Adding the calculated rows gives 97,440 cubic inches. Applying the NIST conversion factors above gives a net geometric volume of approximately 56.39 cubic feet, or 2.0885 cubic yards.
Notice that the landing uses its full height above the base. Treating it as a thin slab would omit the concrete beneath it in this solid construction model. Conversely, using the full-height landing calculation for a platform supported over a void would substantially overestimate the material.
This example includes only the illustrated stair-and-landing shape. Add any separate concrete components using the method below before applying an ordering allowance.
When does the construction method change the calculation?
The visible outline of stairs does not tell you how much concrete is underneath. Check the construction drawings or inspect the proposed formwork before choosing a formula.
Steps over compacted fill: Calculate the space between the finished stair surfaces and the specified fill profile. Subtract only fill that is actually shown and measured. A manufacturer’s concrete steps construction guide describes compacted base preparation and construction incorporating fill. Your estimate must follow the support arrangement selected for your project.
Stairs supported by a sloping slab: Use the designed slab geometry and the concrete forming the stepped surface above it. Work from a dimensioned structural section. Thickness measured perpendicular to a sloping slab differs from vertical thickness; using the wrong measurement changes the volume. Have the designer confirm the quantity boundaries if the drawing is unclear.
Hollow or precast stairs: Measure any site-poured foundations, pads, or other specified concrete separately. The outer dimensions of the stair unit do not represent its concrete content.
For additional rectangular components, use length × width × concrete thickness. Include footings, pads, and below-base extensions only where they fall outside volumes already counted. Mark each component on the sketch as you calculate it; this makes overlaps easier to spot.
Do not subtract a guessed percentage for reinforcement, fill, or empty space. Use the actual designed geometry, and have structural changes reviewed before reducing concrete thickness or altering support.
How much extra concrete should you allow?
The National Ready Mixed Concrete Association recommends ordering 4% to 10% above the volume estimated from plan dimensions for contingencies in CIP 31, Ordering Ready Mixed Concrete (2023).
Use:
Planning quantity = total measured concrete volume × (1 + allowance percentage ÷ 100).
Applying a 10% allowance to the unrounded worked-example volume gives approximately 62.03 cubic feet, or 2.30 cubic yards. This is a planning quantity before adjustment to the supplier’s available ordering increment.
Choose the allowance with the supplier or installer after checking the forms and base. Explain any irregular excavation or difficult placement conditions. If pumping is planned, ask whether the placement method requires an additional quantity beyond the stair estimate.
An allowance should cover reasonable uncertainty. If you discover a substantial depression beneath the forms or a missing foundation component, measure it and revise the geometric total. Hiding a known omission inside a larger percentage makes the estimate harder to check.
For ready-mix delivery, ask the producer how to round the final quantity. Use its actual ordering increment rather than assuming every supplier accepts the same fractions of a yard.

How do you convert the volume into bags?
Use the mixed-concrete yield printed on the selected bag, expressed in cubic feet. Bag weight alone does not establish the volume of every concrete formulation.
Bags required = planning volume in cubic feet ÷ published yield per bag, rounded up to a whole bag.
For reference, a manufacturer’s concrete-mix technical specifications, revised October 2022, give the following approximate yields for that particular mix:
| Bag weight | Published mixed yield | Calculated bags per cubic yard, before allowance |
|---|---|---|
| 40 pounds | 0.30 cubic feet | 90 |
| 60 pounds | 0.45 cubic feet | 60 |
| 80 pounds | 0.60 cubic feet | 45 |
These figures are product-specific examples. Check the current packaging for the concrete you intend to use.
Using the last yield in the table, the worked example’s unrounded planning volume divided by the yield gives approximately 103.38 bags, which rounds up to 104 bags. The contingency is already included; adding it again would inflate the estimate.
Do not estimate yield by measuring loose dry powder in a bucket. Use the manufacturer’s mixed-volume figure and its specified mixing-water instructions. Extra water is not a way to increase usable yield.
What should you confirm before arranging the pour?
Turn the estimate into a placement plan. If mixing bags, establish the mixer’s permitted batch capacity, the number of batches, and how helpers will move and place the material. Check that the planned mixing rate can support the pour sequence specified by the installer. The manufacturer’s steps construction guide emphasizes completing the project as a coordinated placement.
For delivered concrete, tell the producer the quantity, required project specifications, placement method, access conditions, and delivery schedule. Discuss freezing exposure when specifying exterior concrete. NRMCA’s ordering guidance (2023) addresses these ordering details and warns that excessive water addition can reduce strength and durability.
Make the route from the delivery or mixing location to the forms ready beforehand. Assign responsibility for receiving the concrete, placing it, finishing the treads, and starting curing. Resolve the foundation, reinforcement, form bracing, and connection details with the installer before concrete arrives.
How do you work safely and reopen the steps?
Wet concrete can cause chemical burns, and dry cement-containing dust can harm eyes and airways. OSHA’s Concrete Manufacturing safety guidance (2004) recommends alkali-resistant gloves, waterproof boots, protective clothing, and eye protection. Control dust and follow the product’s safety instructions for respiratory protection.
Keep wet material out of gloves and boots, and remove contaminated clothing promptly. Wash exposed skin immediately with clean running water. For concrete splashed into the eyes, OSHA advises flushing with water for at least 15 minutes and obtaining hospital treatment. Seek immediate medical care for suspected cement burns, as advised in OSHA’s Portland cement skin-protection guidance (2008).
After finishing, follow the specified curing method. NRMCA’s Curing In-Place Concrete guidance explains that curing maintains suitable moisture and temperature so concrete can develop strength and durability. When water curing is used, avoid alternating wetting and drying.
Keep the stairs barricaded until the manufacturer’s or installer’s requirements for foot traffic are satisfied. Follow separate instructions for removing forms and applying heavier loads. Surface hardness alone does not establish readiness; the mix, temperature, curing conditions, and structural arrangement affect when the stairs can safely enter service.